SECO — Operational reportsOperational overviewpage 1 of 5

0 of 41 decided
Walk through the report and mark each visual Keep or Exclude. Add a comment anywhere you want something different — what is missing matters as much as what is wrong.

Operational overview

Where do we stand across every live project, and what needs attention this week?

Seco Tools
Operational reporting
Projects in delivery — as at today1.1
as at 29 Sep
25
Computed on 98 of 384 projects — Active, with a stage snapshot
286 not counted — not Active
Smartsheet
1.1
not decided
Allocation against capacity — next 4 weeks1.2
as at 29 Sep · Not affected by customer, segment or stage filters
73.8%
Computed on 42 of 42 active people with capacity in the window
Planned hours, not hours worked. This report holds no actual hours.
Smartsheet and DatabricksQuestion for you: Is this the EPMS allocation, as a percentage of weekly capacity?
1.2
not decided
On-time gate rate — rolling 90 days1.3
as at 29 Sep · Not affected by Status
62.2%
Computed on 241 gates passed in the rolling 90 days
533 not yet passed and 2298 passed outside the window are not counted
No source yetQuestion for you: Does EPMS record a planned and an actual date for every gate?
1.3
not decided
Overdue actions — as at today1.4
as at 29 Sep
211
Computed on 963 open actions across 98 Active projects
6 not counted — open on Delivered or Closed projects, outside the Status slicer
SmartsheetQuestion for you: How do action logs work in EPMS: owner, due date, closed?
1.4
not decided
Request-to-route cycle time — selected period1.5
as at 29 Sep · Not affected by Status
19days
Computed on 423 of 447 requests carrying a route decision
24 not counted — no route decision recorded yet
SmartsheetQuestion for you: Which two dates should this clock run between, and how are the days counted? Do you want 'requests reviewed within 3 days' here?
1.5
not decided
Feedback completion rate — selected period1.6
as at 29 Sep · Not affected by Status
84.7%
Computed on 268 closed and delivered projects — 228 with feedback
116 not counted — not yet closed, so closure feedback cannot be due
Smartsheet
1.6
not decided
Needs attention this week
two per cause, oldest first within cause · showing 8 of 269 · rows drill through
1.9
269 blocker items need a decision as at 2026-09-29: 76 Overdue action, 7 Gate stalled, 17 Approval unresolved, 51 Awaiting customer, 48 Awaiting partner, 44 Resource unavailable, 26 No activity. Each row names its owner. Grouped by cause, oldest first within each cause.
Blocker cause (shown of total)Project or personOwneri-HubWhat is happeningDecision neededDays blocked
Overdue action(2 of 76)Turbine blade root millingAnders Lindqvisti-Hub US5 overdue actions, oldest due 2026-05-03Owner to confirm a new due date or close the action149 dPerson →
Overdue action(2 of 76)Titanium pocket roughingStephen Hollinsi-Hub UK2 overdue actions, oldest due 2026-05-09Owner to confirm a new due date or close the action143 dPerson →
Gate stalled(2 of 7)Impeller five-axis strategyMatthias Brandti-Hub GermanyPre-sales & offer stalled since 2026-08-23, 14 days past its planned date of 2026-08-09Agree a new gate date, or escalate to the gate owner37 dProject →
Gate stalled(2 of 7)Chip evacuation studyHarriet Sladei-Hub UKAssessment & qualification stalled since 2026-08-24, 14 days past its planned date of 2026-08-10Agree a new gate date, or escalate to the gate owner36 dProject →
Approval unresolved(2 of 17)Thread milling standardisationRachel Okonkwoi-Hub UKApproval step unresolved 84 days beyond its 5-day SLAApproval outstanding — response policy not set84 dProject →
Approval unresolved(2 of 17)Impeller five-axis strategyRachel Okonkwoi-Hub UKApproval step unresolved 78 days beyond its 10-day SLAApproval outstanding — response policy not set78 dProject →
Awaiting customer(2 of 51)Titanium pocket roughingStephen Hollinsi-Hub UKTasked to a customer contact on 2026-03-29, no responseCustomer response outstanding184 dProject →
Awaiting customer(2 of 51)Automated tool presettingGareth Pembertoni-Hub USTasked to a customer contact on 2026-04-07, no responseCustomer response outstanding175 dProject →
Awaiting partner(2 of 48)Deep hole drilling trialPriya Raghunathani-Hub UKTasked to a partner contact on 2026-06-07, no responsePartner response outstanding114 dProject →
Awaiting partner(2 of 48)Superalloy grooving trialIngrid Bergströmi-Hub USTasked to a partner contact on 2026-06-08, no responsePartner response outstanding113 dProject →
Resource unavailable(2 of 44)Turbine blade root millingHeller_H6000i-Hub USWork planned in the week of 2026-09-28, in which Heller_H6000 has no available capacityNo capacity that week — reassign or replan1 dProject →
Resource unavailable(2 of 44)Superalloy grooving trialXiaoling Cheni-Hub USWork planned in the week of 2026-09-28, in which Xiaoling Chen has no available capacityNo capacity that week — reassign or replan1 dPerson →
No activity(2 of 26)Aluminium high-feed roughingElin Hallgreni-Hub USNothing recorded since 2026-05-12, quiet beyond 30 days since 2026-06-11Confirm the project is still live, or close it110 dProject →
No activity(2 of 26)Crankshaft turning insert trialFiona MacLeodi-Hub UKNothing recorded since 2026-05-28, quiet beyond 30 days since 2026-06-27Confirm the project is still live, or close it94 dProject →
▲ overdue action · ● gate stalled · ■ approval unresolved · ◀ awaiting customer · ▶ awaiting partner · ▼ resource unavailable · ◆ no activity. Days blocked uses each cause’s own clock.
Projects by stage, last 12 months1.7
  • Intake
  • Qualification
  • Pre-sales
  • Agreement
  • Delivery
060120OctNovDecJanFebMarAprMayJunJulAugSep
Stage at each month end, read from the daily project snapshot. Five stage groups, not eight stages. Current month is partial. Not affected by Status.
No source yet
1.7
not decided
Open projects by i-Hub1.8
i-Hub UK42i-Hub US29i-Hub Germany27
98 open projects in total as at 2026-09-29.
Smartsheet
1.8
not decided
As at 29 Sep 2026 · EPMS refreshed 29 Sep 2026 06:12 UTC · one source, no second system